Posted 9/24/2026
Main Street Sidewalk Replacement Project
Today the Contractor topsoiled and seeded along the new sidewalk. They were unable to pour today due to other conflicts.
Tomorrow the Contractor will install curb forms and pour new curb on both sides of Main Street at the Grove Street crossing. They will also pour new curb at the First Congregational Church Main Street entrance, and replace a cracked sidewalk panel in front of the cemetery at 34 Main Street.
Now that the Contractor has installed seed and hay mulching, we ask residents to please water their lawns to help the grass grow.
The contractor provides the best prediction of their next work cycle. Please keep in mind that construction is a fluid process, and sometimes plans must change based on weather, conditions found in the field, or other factors.
Throughout construction, we will send daily emails about progress and the anticipated schedule, as they may relate to access and disruptions to adjacent properties. For general questions or to receive daily project email updates, please email MainStreetSidewalks@dlhce.com to request to be added to the project email distribution list.